McFarlane Aviation Products FAA-PMA Replacement Aircraft Parts

In 2012 McFarlane completed a building expansion project to add 24,000 square feet to our current facilities. A big thank you to Mar Lan Construction for their hard work!  

 

  

Preliminary ground work on May 2, 2011 and official groundbreaking on July 8, 2011.

 

 

Early dirt work and arrival of heavy equipment on July 11, 2011.

 

 
Ground preparation in July 2011 and framing begins on August 15, 2011.

 

 
Aerial view of facilities on August 26, 2011 and raising of beams on September 12, 2011.

 

 
Beautiful sunset on September 23, 2011, and Dave and Dan McFarlane review building progress on September 26, 2011.

 

 
West walkway construction on September 26 and October 3, 2011.

 

 
West walkway construction on October 10 and October 17, 2011.

 

 
Aerial view of facilities on October 15, 2011 and McFarlane employees put their handprints in concrete on October 27, 2011.

 

 
View of the west-facing entrance on October 24 and November 7, 2011.

 

 
Both buildings on November 14, 2011 and the courtyard on November 7, 2011.

 

 
South-facing walkway on December 5, 2011 and the view from the runway on November 14, 2011.

 

 
Interior views on November 16 and December 26, 2011.

 

 
Interior views in January 2012.

 

  
Employee excitement for building completion in February 2012 and the official ribbon cutting on March 14, 2012.

 

 
Control department and fabrication and spacious kitchen on April 6, 2012.

 

 
 R&D/Maintenance area